Forecast a project from similar past projects
Forecast a project from what similar projects really cost, not from your own plan.
2 min read · Level 3 · Vidyaa Editorial
You are asked how much a new project will cost. The usual answer comes from the plan itself: add up each part and the total is the forecast. Bent Flyvbjerg wrote in 2006 that this is risky. Inaccurate forecasts of costs, demand and other effects are a major source of risk in project management.
He explains the errors in terms of optimism bias and strategic misrepresentation. In the first, planners hope for too much. In the second, the forecast is misleading in a way that suits the plan.
His method is called reference class forecasting. The forecast is based on the actual performance of a reference class, which is a group of comparable projects. It is not based on the plan for the new one. In this way it can bypass both problems. The idea behind it comes from work on decisions under uncertainty that won the 2002 Nobel Prize in economics. The paper presents the first practical instance, for the costs of large transport projects.
Try this: before you forecast a project, list three similar past projects and use their average as your starting point.
Listing three similar past projects is a small version of the method, and the paper did not test that shortcut.
Source: Flyvbjerg (2006), a paper on forecasting the cost of projects.[1]